The delivery of the USS John F. Kennedy, the second ship in the new Ford class of U.S. Navy aircraft carriers, could be delayed by up to two years.

Why It Matters

Many U.S. Navy shipbuilding projects have been plagued by setbacks and ballooning costs, including the USS Gerald R. Ford, the first Ford-class aircraft carrier. The Gerald R. Ford was commissioned, or formally marked as in active service, by President Donald Trump during his first term in office.

Read More on News

What To Know

The USS John F. Kennedy, also known as the CVN-79, was expected to be handed over to the U.S. military in July this year, but will instead be ready in March 2027, according to U.S. Navy budget documents for the coming year. The delay was first reported by the USNI News outlet attached to the Naval Institute non-profit on Monday.

A Navy spokesperson told Newsweek that the "formal delivery" of the aircraft carrier "is anticipated in March 2027," although the military is "exploring opportunities for preliminary acceptance of the vessel prior to formal delivery."

The Navy is "coordinating closely with stakeholders to ensure the fastest possible transition to fleet operations and a combat capable carrier," the spokesperson said.

USS Gerald Ford AC

...

The USS John F. Kennedy is the second of the new Ford-class aircraft carriers, replacing the decades-old Nimitz-class.

The third aircraft carrier in the class, the USS Enterprise, will be delivered in July 2030, rather than September 2029, according to the U.S. Navy budget documents. The delay was chalked up to issues getting hold of materials for the vessel, and hold-ups with industry and supply chains.

The delay in delivery of the USS John F. Kennedy is "not surprising," bearing in mind the changes it needed after its initial building phase and "challenges throughout the U.S. shipbuilding industry," said Robert Murrett, a retired U.S. Navy vice admiral who is now a professor of practice of public administration and international affairs at Syracuse University.

The USS John F. Kennedy needs to take on board the lessons from the first of the new class of aircraft carriers, Murrett told Newsweek. It also needs to build in new technology, like updated radars, and equipment for F-35C fighter jets, Murrett said.

Although the U.S. Navy's fleet of operational carriers will hit just 10 for a year, he added, "this can be mitigated with careful management of existing CVNs' maintenance and overhaul schedules, as well as equally careful management of longer deployments for our carrier sailors, which is already an issue." CVN is shorthand for nuclear-powered aircraft carriers.

The Navy budget documents put the delay to the USS John F. Kennedy down to the Advanced Arresting Gear (AAG) for the ship and Advanced Weapons Elevator work.

AAG is a new system for the second and third Ford-class aircraft carriers, according to the military. It is designed to make sure aircraft landing on the carriers slow down quickly and safely.

Advanced Weapons Elevators help move weapons and ammunition around a ship.

What People Are Saying

The U.S. military has hailed the USS John F. Kennedy as "the most agile and lethal combat platform globally," kitted out with "improved systems" that link the carrier up more closely with other forces.

Update 07/08/25, 12:30 p.m. ET: This article was updated with a statement from a Navy spokesperson.