By Soo Kim
Reporter
0
Share
Newsweek is a Trust Project member
See more of our trusted coverage when you search.Prefer Newsweek on Googleto see more of our trusted coverage when you search.
The upper deck of the Yellow River tunnel in Jinan, the capital of the province of Shandong in East China, was completed on Tuesday, marking a major breakthrough for the world's largest-diameter underwater shield tunnel, according to Xinhua, the Chinese state news agency.
The upper deck of the tunnel, which is located on Huanggang Road, was finished with the pouring of the final cast-in-place roadway slab, reported the Global Times, the state-owned Chinese newspaper.
The tunnel is China's first single-bore, double-deck shield tunnel to pass beneath the Yellow River, an engineer involved in the project told the Global Times. Spanning 5.75 kilometers (around 3.6 miles), the tunnel accommodates six lanes across two levels, with a speed limit of 60 kilometers per hour (around 37 miles per hour).
Read More on Travel
About 3.3 kilometers (around 2 miles) of the tunnel were constructed using the shield tunneling method, deploying a 17.5-meter diameter (around 57 feet) tunnel-boring machine (TBM), according to Xinhua.
The continuous 2-mile excavation was done without cutterhead replacement, which is an unprecedented achievement under such conditions, according to the Global Times. The project set records for 17-meter-class shield tunneling, with a peak daily advance rate of 18 meters (around 59 feet) and a monthly advance of 426 meters (around 1,397 feet).
Zhou Xiang, a senior engineer with China Railway 14th Bureau Group and the project's chief technical expert, noted that, following the primary tunnel lining, secondary structural works are necessary inside the tunnel.
The upper roadway slab, installed at the tunnel's central section, divides the bore into two levels and serves as the structural "backbone" for upper-deck traffic, according to Xinhua.
Zhou said, according to the Global Times: "Construction of the upper slab takes place within the confined space of the shield tunnel, where numerous embedded components of varying types must be precisely installed. Positioning errors must be controlled within millimeter-level tolerances."
The team behind the project adopted a modular design and an independent traveling system for the tunnel's construction to help mitigate any errors or other challenges.
Multiple platforms were operated in parallel, forming an assembly-line process for reinforcement binding, formwork installation, and concrete curing, which significantly enhanced efficiency. A dedicated lower-level transport corridor allowed for the smooth flow of materials and workers, reported the Global Times.